The well has been drilled. They hit water at just about 300 feet. Mike estimated that the water was flowing at about 20 gal per minute - apparantly this is very good. Yay!

The well pump has been installed, and we should be able to get a water sample for testing this week. Once that is done, we can close on the land purchase and apply for a building permit.