The rough plumbing continues to progress nicely.















Here is the back of downstairs shower. Fascinating - isn't it?!



















And here is the set up for the upstairs shower.



















And here is our plumbing contractor on the job.
















But wait a minute! What are all these pipes doing in my dance room?!!















And here is what else is going on in my dance room.

I don't see any walls framed yet, do you?

I would like to at LEAST have the walls framed so it is ready when the drywall contractors come in.

Hmmmm... seems like the dance room is a low priority.

Do I sound like a spoiled brat?














The electrical has slowed down a bit this week as our electrician had some health issues to attend to.



















Dean is working on the outside installing wooden plates where the exterior lights will be mounted.